The customer is holding back the final payment. How long do you have? Lien and payment-claim deadlines in California, Texas, Florida, NSW, Victoria and Queensland

While you argue about a crack or a credit, a deadline may be running. It's roughly three months to lien in California, Texas and Florida, and up to 12 months for a payment claim in New South Wales. In Victoria and Queensland, a job at the customer's own home often has no such fast route.

Published November 5, 2026. Rules from the California Civil Code, Texas Property Code chapter 53 and the Texas Constitution, Florida Statutes chapter 713 (2026), the NSW Building and Construction Industry Security of Payment Act 1999 and its 2020 Regulation, Victoria's Security of Payment Act 2002 (version as at June 24, 2026) and Domestic Building Contracts Act 1995, and Queensland's Building Industry Fairness (Security of Payment) Act 2017, read that day.

The short version

  • California: a direct contractor records a mechanics lien within 90 days after completion, or 60 days after the owner records a notice of completion or cessation, whichever comes first. Then you have 90 days to sue on it.
  • Texas: on a residential job, the lien affidavit is due by the 15th day of the third month after the month your work ended. On a homestead, that only helps if the contract met a longer list of conditions, most of them before work began.
  • Florida: the claim of lien is recorded within 90 days after your final furnishing of labor or materials. The lien then lasts one year unless you sue.
  • New South Wales: a payment claim can be served for 12 months after the work was last carried out, or longer if the contract allows. The Act's text covers owner-occupiers, but a NSW Government FAQ says otherwise for plumbing and electrical work, so we'd check before relying on it.
  • Victoria and Queensland: the Security of Payment Acts generally leave out a direct contract with the person whose home it is. That leaves the regulator's dispute process, then the tribunal or court, with a six-year general limit on contract claims.
  • These are deadlines for particular tools. Missing one loses that tool, and an ordinary claim for the debt has its own separate time limit. All of this assumes a licensed contractor dealing directly with the owner. Subcontractors have earlier notice steps, covered below.

Two posts in r/Contractor this past month had the same shape. In one, a concrete crew came back to repair a small crack in a patio, and the customer still refused the remaining $6,000. In the other, a California contractor was owed $12,000 after an argument over window casing, had paused the last day of trim, and asked whether to lien. These are anecdotes from a forum, and we can't verify either one.

The law in most of these places doesn't wait for the argument. The clocks below generally run from the end of the work, not from the day the customer stops answering, and these rules don't pause them for a dispute. This note is about those dates. It sets the six rules side by side, then goes through what starts each clock, what has to be in place for the tool to exist at all, what changes if you're the subcontractor, and how we'd keep the dates in view.

Six clocks side by side

Here's one hypothetical standalone job: a direct contract with an owner who lives in the home, a licensed contractor, no other contract connected to the work, nothing recorded by the owner, and no longer period in the contract. Assume everything ended on Wednesday, October 14, 2026: your last work, the whole job and the contract. On a real job those can be different dates, and each place counts from its own one.

PlaceWhat's being timedLast day on this jobWhat comes next
CaliforniaRecording a mechanics lienJanuary 12, 2027 (earlier if a notice is recorded)Sue within 90 days of recording
TexasFiling a lien affidavitJanuary 15, 2027, if the homestead conditions were metCopy to owner within 5 days; sue by the first anniversary of the last filing day
FloridaRecording a claim of lienJanuary 12, 2027Serve before or within 15 days of recording; sue within 1 year of recording, or sooner if the owner contests or goes to court
NSWServing a payment claim under the ActOctober 14, 2027, if the Act applies (see the FAQ problem below)Customer has 10 business days to answer with a payment schedule
VictoriaNo payment claim on this job; debt route through conciliation, then VCATNo short deadline; six-year general limit on contract claims, counted from when the claim aroseCertificate of conciliation before VCAT, if the Domestic Building Contracts Act applies
QueenslandNo payment claim on this job; debt route through the QBCC process, then QCATNo short deadline; six-year general limit on contract claims, counted from when the claim aroseQBCC outcome letter before QCAT

Those rows aren't like for like. The American dates keep a claim against the property alive, the NSW date keeps a fast money claim alive, and the six years is an outer limit for suing on the debt. The next three sections take the American clocks, because they end soonest.

California: 90 days, and a shorter clock nobody has to tell you about

Civil Code section 8412 says a direct contractor can't enforce a lien unless it records a claim after finishing the direct contract and before the earlier of two dates: 90 days after completion of the work of improvement, or 60 days after the owner records a notice of completion or cessation.

Three details in that rule matter in a payment dispute.

Recording isn't the end of it. Section 8460 gives you 90 days after recording to start a court action, or the lien expires, unless you and the owner agree to extend credit and record notice of that. Section 8416 sets what the claim must contain, including a Notice of Mechanics Lien served on the owner. Section 8422 says a claim that willfully includes work or materials not furnished for that property forfeits the lien. And Business and Professions Code section 7031 bars a collection action for work that needs a license unless you allege you were licensed the whole time. A direct contractor doesn't owe the owner a preliminary notice, under section 8200(e): it only goes to a construction lender, if there is one.

Texas: a date counted in months, and a door that closes before the job starts

Texas counts differently from California. Property Code section 53.052 gives an original contractor on a residential construction project until the 15th day of the third month after the month its work was completed, terminated or abandoned.

Because the count runs by month, the day you finished within that month changes nothing. Finish on October 1 and January 15 is 106 days away. Finish on October 31 and it's 76 days away. Anyone who keeps "about 90 days" in their head for every state could be two weeks late here.

The bigger question comes earlier, though. Section 53.254 says that to fix a lien on a homestead, there must be a written contract with the owner, executed before the work or materials are provided, signed by both spouses if the owner is married, and filed with the county clerk. For repair and renovation work, article XVI, section 50(a)(5) of the Texas Constitution adds more. The contract must let the owner rescind without penalty within three days, and it can be signed by the owner and spouse only at the office of a third-party lender making a loan for the work, an attorney or a title company. If the owner applied in writing for credit for the work, it can't be signed before the fifth day after that application. The rescission and five-day conditions have a narrow exception for immediate health or safety repairs the owner acknowledges in writing. The lien affidavit also has to carry a printed notice at the top saying that it's not a lien, only an affidavit claiming one.

A repair approved by text message doesn't meet that list. As we read it, on a homestead repair job without those steps, the lien route is likely closed before any dispute starts, and the January date doesn't help. That leaves a claim for the debt itself. The signing steps belong before the work, so on a job at the owner's home we'd look at them when the contract is written.

When the lien is available, section 53.055 requires a copy of the affidavit to go to the owner within five days after filing, and section 53.158 requires suit by the first anniversary of the last day you could have filed. A written agreement with the current record owner, made before that time runs out and recorded in the same county, can extend it up to the second anniversary of filing.

Florida: 90 days from your last work, then a clock the owner can shorten

Florida looks like California on the calendar, but it's counted from your own last day. Section 713.08(5) allows a claim of lien any time during the work and up to 90 days after the final furnishing of labor, services or materials by the lienor. If the contract is terminated under section 713.07(4), the limit can come earlier.

Three steps follow, each with its own date. Section 713.08(4) has the claim served on the owner before recording or within 15 days after, and late service makes it voidable to the extent someone was prejudiced. Section 713.06(3)(d) says a contractor must give the owner a final payment affidavit at least 5 days before suing to enforce the lien, even with no subcontractors on the job, and has no lien or right of action against the owner while in default on it. And section 713.22 ends the lien one year after recording unless you've sued.

That year can shrink. The owner can record a notice of contest under section 713.22(2), which limits you to 60 days from service. Or an interested party can file a complaint under section 713.21(4), and the summons gives you 20 days after service to show cause, with the lien cancelled if you don't. If it were our file, any notice or court paper about a lien would go to a lawyer the day it arrived.

A callback raises a question in all three states: if you went back in December to fix the crack, did the clock restart? In Florida, no. Section 713.01(12) says final furnishing doesn't include correcting deficiencies in work you've already done. Texas's definition of completion, in section 53.001(15), likewise leaves out warranty work and repair of the work performed. California's section 8180 doesn't address it in those words, so there we'd diary from the first finish and not count on a later date. New work under the contract is a different matter, and worth a lawyer's reading.

New South Wales: 12 months, with a warning label

Crossing to Australia, the tool changes. What we're describing here is a claim for money with a short forced reply, not a charge on the house. (The lien in section 11(3) of the NSW Act reaches only unfixed plant or materials you supplied.)

NSW used to exclude owner-occupiers from its Security of Payment Act. Section 7(2)(b) is now repealed, and the NSW Government says the change took effect for owner-occupier contracts entered into from March 1, 2021. On the Act's text, a payment claim can now go to a homeowner, and a final payment counts as a progress payment under section 4.

Two conditions sit in front of all that. Section 8(2) removes the entitlement if the contract doesn't comply with section 4 of the Home Building Act 1989, or the work breached section 92 of that Act. And a head contractor has to attach a supporting statement that subcontractors have been paid, on the approved form for owner-occupier contracts (section 13(7)).

Now the warning label. The NSW Government's Security of Payment FAQ says the Act doesn't apply to a direct contract with a person who lives at the site where the work is residential building work under $5,000, electrical wiring, plumbing, draining and gas fitting, or air conditioning and refrigeration work. That doesn't match the current Act or the 2020 Regulation as we read them. We can't find that carve-out there, the FAQ doesn't cite a section, and the Government's own changes page says the owner-occupier change applies from March 2021. The FAQ may be left over from older rules, but that's our guess. For a plumber or electrician, this is the very job the note is about, so if it were us we'd have a NSW construction lawyer confirm it on the specific contract, well inside the 12 months.

Victoria and Queensland: usually no fast route on the customer's own home

NSW's change is what makes the other two states stand out, because neither has made it.

In Victoria, section 7(2)(b) of the Security of Payment Act leaves out a domestic building contract between a builder and a building owner, unless the owner is in the business of building residences. Section 7(2)(ba) also leaves out work of a kind referred to in section 6 of the Domestic Building Contracts Act relating to a residence. As we read it, that's what reaches the plumbing-only and electrical-only contracts the regulations take outside the domestic building rules. That paragraph has two exceptions: the person you work for is in the business of building residences, or your work is, or is part of or incidental to, work under another construction contract. So a standalone contract with the homeowner looks excluded, while a plumber on a separate contract during a wider renovation needs a closer look. The 2025 amendments, in the version as at June 24, 2026, rewrote the claim procedure but left these exclusions in place.

What's left there depends on the contract. Under a domestic building contract, section 27 of the Domestic Building Contracts Act says an unpaid amount that's due creates a domestic building dispute, and section 56 says you can't apply to VCAT without a certificate of conciliation. The Building and Plumbing Commission runs conciliation and can issue a binding dispute resolution order or a certificate that opens the way to VCAT. An unpaid single-trade contract outside that Act is a plain contract debt, and we'd ask a lawyer which forum suits it.

In Queensland, section 61(2)(b) of the Building Industry Fairness Act leaves out a contract for domestic building work with a resident owner, to the extent it relates to the building where they live or intend to live. The QBCC says it can help the parties reach an agreement but has no power to require someone to pay, and that once its process ends, both parties get a letter allowing them to apply to QCAT.

The states split on landlords. Queensland's exclusion turns on a resident owner: an individual who intends to live in the building on completion or within six months after it, not counting relevant owner-builders and building contractors (section 61(5) and Schedule 1B of the QBCC Act). So as we read it, a landlord who doesn't meet that definition can receive a payment claim. A final claim is due by the longest of any contract period, 28 days after the last defects liability period, and six months after completion of the work or supply (section 75(3)). The respondent then has the contract's time or 15 business days, whichever ends first, to give a schedule, unless it pays in full by the due date (section 76). Victoria's paragraph (b) doesn't turn on who lives there, so a rental home under a domestic building contract stays out, unless that owner is in the business of building residences.

Neither state's route has a 90-day cliff. Contract claims are generally limited to six years in both, counted from when the cause of action arose, under section 5 of Victoria's Limitation of Actions Act 1958 and section 10 of Queensland's Limitation of Actions Act 1974. For an unpaid debt that generally points to when payment fell due and wasn't made, not your last day on site, so the contract's due date is one more date to record.

If you're the subcontractor, the first date is much earlier

Everything above assumes you contracted with the owner. Work for a builder or another contractor on the same house and the order of events changes, because the first step comes while you're still on the job.

Late notice can cut or defeat your protection, and some notices recur monthly. If it were us, they'd go on the job calendar at setup, not wait for the invoice to go overdue.

How we'd keep the dates in view

The sections above add up to several dates per job, each checked against that job's facts. If we were running the office for a job like the patio, here's what we'd do.

Back to the patio. Say the crew finished the whole job in California on October 14 and went back to repair the crack in late October. The argument might take weeks, and it might even end well. On our calendar, though, January 12, 2027 would still be the date, and the decision about what to do would belong to the owner of the business and their lawyer in early December, not in the second week of January.

Want someone keeping the dates?

Invoicing the same night, polite reminders on overdue invoices and a weekly list of who still owes you are part of what Taiwan Rep's overnight office does. See what we handle and what stays with you. Legal advice stays with you and your lawyer, and so does the decision to lien or claim.

Get started

This note summarises rules for unpaid work in California, Texas, Florida, New South Wales, Victoria and Queensland as we read them on November 5, 2026. It isn't legal or tax advice, and we aren't lawyers. Dates in the examples are hypothetical. Each rule has exceptions and formal requirements that aren't all covered here, a missed step can lose the right altogether, and a lien or payment claim is worth taking to a construction lawyer in that state before you rely on it. Other states and territories have their own rules.

Sources